5.- Cuestionario.

1.-The PMP will not contain: company procedures.

2.-The PMP: Converts projects strategy into executable activities.

3.-Which of the following would not normally be the responsibility or accountability of the 

4.-project manager: realizing the benefits from the projects.

5.-The project management plan defines:  the way in which the project will be planed and managed.

6.-Resource limited scheduling ensures that: the amount of available resources are not exceeded.

7.-Resource smoothing is: Scheduling of activities, so that the specified project duration is not exceeded.

8.-The following are true about resource scheduling except : resource scheduling is used to develop WBS:

9.-RACI is: A code used in a responsibility assignment matrix.

10.-The primary purpose of a WBS is: to define the scope of the project.

11.-The critical path is: the longest path through the network.

12.-Which of the following is not normally a milestone: all activities on the critical path.


13.-Gantt charts are useful in presenting: Activity start and finish dates together with excepted durations. 